PROJECT COMPLETED

Manresa Road

  • ClientMultiplex UK
  • Duration N/A

A sensitive demolition and extensive façade retention project located in the heart of Chelsea

Manresa Road, located in the heart of Chelsea, is an historic building which was formerly a hospital.

So that an exclusive development of sixteen luxurious apartments and one villa could be constructed by the developer, McGee provided a range of decontamination, demolition and civil engineering services.  This involved all demolition works and extensive groundworks; including the design and installation of a 300 metre length of secant piled wall, 250t of temporary steel flying shores and the excavation of 40,000m3 for a new basement car park.

Although the façade was retained through the installation of a bespoke structural steel frame support system that ran the full 100 metre length of the building, the developer had plans for a strikingly modern rear elevation.  The retained façade required the extensive temporary works to support the structure prior to incorporation into the main building.  The façade support was situated on a series of mini-piles which were constructed in a restricted working area.

Due to the sensitive residential location of the project, including an adjacent school, McGee maintained strict noise, vibration and dust monitoring throughout the life of the project.

Contact Us
Print Page
Print Friendly
Email Page

Services covered

  • Decontamination
  • Demolition
  • Civil Engineering

Market

  • Residential

Scope of Work

  • Asbestos survey & removal
  • Removal of hazardous substances
  • Soft strip
  • Erection of perimeter scaffold & fans
  • Demolition of all structures & basements
  • Controlled demolition of upper structures
  • Design & Installation of structural decks
  • Façade retention design & installation
  • Design & Installation of basement propping
  • Excavation of basement
  • Processing & recycling scrap metal