Middlesex Site – Newsletter

This coming month’s activities:

– Sheet pile probing works and basement slab and foundations removal, north of the Chapel

– Install propping to sections of Cleveland St and Mortimer St

– Commence probing works to double basement section of Cleveland St and Mortimer St

– Continue with the removal off-site of the crushed concrete

– Temporary relocation of site vehicular access / egress to Cleveland St

– External repair to the chapel

We have now installed all vibration noise and dust monitors both on and off-site. The report from our monitoring equipment shows that any noise and vibrations caused in the previous month were within acceptable levels, as  set out in British Standards.